Shortcuts to the text Main Menu Shortcut
Facilities safety business division

Nuclear Power Business Headquarters

Responsible for the safety of national energy infrastructure
Nuclear Power Business Headquarters

Daum Engineering Co., Ltd. is a company that strives to become a leader in the nuclear business industry with the motto of "next generation technology pursuit," and has excellent technology and experienced nuclear power plant civil engineers. The nuclear business division is conducting service and maintenance work of related companies such as Korea Hydro & Nuclear Power Co., Ltd. and Korea Nuclear Environment Corporation. Technicians in the nuclear business sector play an important role in facilitating the project on behalf of the client's service and maintenance work, and contribute to the development of the nuclear industry by efficiently proceeding with the project and securing quality.

Major business areas

  • Inspection of nuclear power plant facilities

    Check through seal, check the post-tensioning system, Inspection of structures, inspection of concrete anchor systems, etc

  • Structure inspection

    Precise and regular inspection of structures and underground structures

  • Perform maintenance work

    Concrete structure maintenance work

Representative Project

2019년 신고리3호기 원전 안전성관련 구조물 초기정밀점검 용역

2019 Shin-Kori Unit 3 Nuclear Power Plant Safety-related Structures Initial Detailed Inspection Service

  • Client
    Korea Hydro & Nuclear Power Co., Ltd. Saeul Nuclear Power Headquarters
  • Location
    Ulsan Metropolitan City
  • Project Period
    2019.04.16 ~ 2020.02.09
  • Completion Year
    2020
2024년 한울3호기 OH관련 구조물 점검 용역

2024 Hanul Unit 3 OH-related Structure Inspection Service

  • Client
    Korea Hydro & Nuclear Power Co., Ltd. Hanul Nuclear Power Headquarters
  • Location
    Uljin-gun, Gyeongsangbuk-do
  • Project Period
    2024.08.07 ~ 2025.02.14
  • Completion Year
    2025
2022년 BNPP 2호기 ILRT 원자로건물 콘크리트 점검 용역

2022 BNPP Unit 2 ILRT Reactor Building Concrete Inspection Service

  • Client
    Korea Hydro & Nuclear Power Co., Ltd. Barakah Nuclear Power Headquarters
  • Location
    United Arab Emirates (UAE)
  • Project Period
    2021.08.10 ~ 2022.04.08
  • Completion Year
    2022
2022년 한빛 5,6호기 14차 OH관련 구조물 점검용역

2022 Hanbit Units 5 and 6 14th OH-related Structure Inspection Service

  • Client
    Korea Hydro & Nuclear Power Co., Ltd. Hanbit Nuclear Power Headquarters
  • Location
    Yeonggwang-gun, Jeollanam-do
  • Project Period
    2022.09.26 ~ 2023.11.25
  • Completion Year
    2023
2022년 월성본부 OH관련 구조물 점검용역

2022 Wolsong Headquarters OH-related Structure Inspection Service

  • Client
    Korea Hydro & Nuclear Power Co., Ltd. Wolsong Nuclear Power Headquarters
  • Location
    Gyeongju-si, Gyeongsangbuk-do
  • Project Period
    2022.03.15 ~ 2023.08.08
  • Completion Year
    2023
2019년 신고리3호기 원전 안전성관련 구조물 초기정밀점검 용역
2019 Shin-Kori Unit 3 Nuclear Power Plant Safety-related Structures Initial Detailed Inspection Service
2024년 한울3호기 OH관련 구조물 점검 용역
2024 Hanul Unit 3 OH-related Structure Inspection Service
2022년 BNPP 2호기 ILRT 원자로건물 콘크리트 점검 용역
2022 BNPP Unit 2 ILRT Reactor Building Concrete Inspection Service
2022년 한빛 5,6호기 14차 OH관련 구조물 점검용역
2022 Hanbit Units 5 and 6 14th OH-related Structure Inspection Service
2022년 월성본부 OH관련 구조물 점검용역
2022 Wolsong Headquarters OH-related Structure Inspection Service

Major Project

Year Project name Client
2022 Gori Units 3 and 4 26th OH-related routine inspection service for containment buildings, etc. Korea Hydro & Nuclear Power Co., Ltd.
2022 Hanul Units 3 and 4 firewall penetration sealant performance evaluation service Korea Hydro & Nuclear Power Co., Ltd.
2021 Shin-Kori Unit 4 nuclear power plant safety-related structure initial detailed inspection service Korea Hydro & Nuclear Power Co., Ltd.
2020 Wolsong Branch Office safety-related structure periodic inspection service Korea Hydro & Nuclear Power Co., Ltd.
2020 Hanbit Units 5 and 6 13th OH-related structure inspection service Korea Hydro & Nuclear Power Co., Ltd.
2019 Hanul Unit 2 containment building and seawater system piping inspection service Korea Hydro & Nuclear Power Co., Ltd.
2019 Hanul Units 3 and 4 containment building internal steel structure inspection service Korea Hydro & Nuclear Power Co., Ltd.
2019 Hanul Units 3 and 4 OH-related ILRT and routine inspection service Korea Hydro & Nuclear Power Co., Ltd.
2019 Hanul Units 1 and 2 safety-related structure detailed inspection service Korea Hydro & Nuclear Power Co., Ltd.
2019 Initial Precision Inspection Service for Safety-Related Structures of Shin-Kori Unit 3 Nuclear Power Plant Korea Hydro & Nuclear Power Co., Ltd.